Amazon Fulfillment Center Project

AmazonFULLv5

Industry

Retail

Challenge

Create early strengths and abrasion resistance, and eliminate conventional curing methods to accelerate access to the slab.

Results

Conveyor systems, large storage racks, and electrical systems were installed just 26 days after the first slab placement, making this one of the fastest Amazon build-outs in a country of its size.

Key Products

E5® Internal Cure, E5® Catalyst

$130M
Manage Spend
700K
Sq ft
17K
Yd of concrete
DLR
Architect

THE AMAZON FULFILLMENT CENTER IN GREENFIELD, IN REPRESENTS ONE OF THE FASTEST BUILD-OUT SITES TACKLED BY CONSTRUCTION CREWS ASSOCIATED WITH THIS PROJECT.

Amazon

E5 Nano Silica

Amazon_Grey2

About Amazon

Amazon is a global e-commerce and tech company founded by Jeff Bezos in 1994. It started as an online bookstore and grew into the world’s largest online retailer. Amazon also leads in cloud computing with AWS, offers streaming via Prime Video, and owns Whole Foods. It’s known for fast shipping and a customer-first approach.

Project Overview

Crews from Compass Construction in Indianapolis, Indiana, worked around the clock to prepare the site and pour footings prior to site concrete work and slab on grade work was performed. Footings were poured late December, and slabs began in February of the following year, just months from initial site preparation. E5 Liquid Nano Silica was selected to achieve early strengths, abrasion resistance and eliminate conventional curing methods to accelerate the access to the slab. Conveyor systems, large storage racks, as well as electrical systems were installed just 26 days after first slab placement, making this one of the fastest Amazon build-outs in the country of its size.

How E5 Elevated Performance

E5 Liquid Nano Silica admixtures give control back to the finishing crews and accelerate construction schedules. E5 Liquid Nano Silica eliminates hardeners, sealers, and curing compounds. When used as a system, E5 creates internal curing, extremely high abrasion results and delivers high FF/FL levels. Crews gain access to the slab much quicker than compared to topically treated slabs.